You are the project manager of the GHY project for your organization. You are about to start the qualitative risk analysis process for the project and you need to determine the roles and responsibilities for conducting risk management. Where can you find this information?
A.
Risk management plan
B.
Enterprise environmental factors
C.
Staffing management plan
D.
Risk register