What project management plan is most likely to direct the quantitative risk analysis process for a project in a matrix environment?

A.
Staffing management plan
Answers
A.
Staffing management plan
B.
Risk analysis plan
Answers
B.
Risk analysis plan
C.
Human resource management plan
Answers
C.
Human resource management plan
D.
Risk management plan
Answers
D.
Risk management plan
Suggested answer: D