You are the project manager of the HJK project for your organization. You and the project team have created risk responses for many of the risk events in the project. A teaming agreement is an example of what risk response?

A.
Acceptance
Answers
A.
Acceptance
B.
Mitigation
Answers
B.
Mitigation
C.
Sharing
Answers
C.
Sharing
D.
Transference
Answers
D.
Transference
Suggested answer: C