List of questions
Related questions
Question 240 - CAP discussion
You are the project manager of the HJK project for your organization. You and the project team have created risk responses for many of the risk events in the project. A teaming agreement is an example of what risk response?
A.
Acceptance
B.
Mitigation
C.
Sharing
D.
Transference
Your answer:
0 comments
Sorted by
Leave a comment first