ExamGecko
Home Home / ISC / CAP
Question list
Search
Search

List of questions

Search

Related questions











Question 246 - CAP discussion

Report
Export

Which of the following processes is described in the statement below?

"It is the process of implementing risk response plans, tracking identified risks, monitoring residual risk, identifying new risks, and evaluating risk process effectiveness throughout the project."

A.
Perform Quantitative Risk Analysis
Answers
A.
Perform Quantitative Risk Analysis
B.
Perform Qualitative Risk Analysis
Answers
B.
Perform Qualitative Risk Analysis
C.
Monitor and Control Risks
Answers
C.
Monitor and Control Risks
D.
Identify Risks
Answers
D.
Identify Risks
Suggested answer: C
asked 18/09/2024
Jendoubi moez
36 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first