Question 249 - CAP discussion

Report
Export

You are the project manager of the GHY Project for your company. You have completed the risk response planning with your project team. You now need to update the WBS. Why would the project manager need to update the WBS after the risk response planning process? Choose the best answer.

A.
Because of risks associated with work packages
Answers
A.
Because of risks associated with work packages
B.
Because of work that was omitted during the WBS creation
Answers
B.
Because of work that was omitted during the WBS creation
C.
Because of risk responses that are now activities
Answers
C.
Because of risk responses that are now activities
D.
Because of new work generated by the risk responses
Answers
D.
Because of new work generated by the risk responses
Suggested answer: D