Question 259 - CAP discussion

Report
Export

You work as a project manager for BlueWell Inc. You are about to complete the quantitative risk analysis process for your project. You can use three available tools and techniques to complete this process. Which one of the following is NOT a tool or technique that is appropriate for the quantitative risk analysis process?

A.
Quantitative risk analysis and modeling techniques
Answers
A.
Quantitative risk analysis and modeling techniques
B.
Data gathering and representation techniques
Answers
B.
Data gathering and representation techniques
C.
Expert judgment
Answers
C.
Expert judgment
D.
Organizational process assets
Answers
D.
Organizational process assets
Suggested answer: D
asked 18/09/2024
Stefano Humphries
40 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first