Question 263 - CAP discussion

Report
Export

The Identify Risk process determines the risks that affect the project and document their characteristics. Why should the project team members be involved in the Identify Risk process?

A.
They are the individuals that will have the best responses for identified risks events within the project.
Answers
A.
They are the individuals that will have the best responses for identified risks events within the project.
B.
They are the individuals that are most affected by the risk events.
Answers
B.
They are the individuals that are most affected by the risk events.
C.
They are the individuals that will need a sense of ownership and responsibility for the risk e vents.
Answers
C.
They are the individuals that will need a sense of ownership and responsibility for the risk e vents.
D.
They are the individuals that will most likely cause and respond to the risk events.
Answers
D.
They are the individuals that will most likely cause and respond to the risk events.
Suggested answer: C
asked 18/09/2024
Christie Clark
40 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first