You work as a project manager for BlueWell Inc. You are working with your team members on the risk responses in the project. Which risk response will likely cause a project to use the procurement processes?

A.
Acceptance
Answers
A.
Acceptance
B.
Mitigation
Answers
B.
Mitigation
C.
Exploiting
Answers
C.
Exploiting
D.
Sharing
Answers
D.
Sharing
Suggested answer: D