Which of the following risk responses delineates that the project plan will not be changed to deal with the risk?

A.
Acceptance
Answers
A.
Acceptance
B.
Mitigation
Answers
B.
Mitigation
C.
Exploitation
Answers
C.
Exploitation
D.
Transference
Answers
D.
Transference
Suggested answer: A