Mark works as a project manager for TechSoft Inc. Mark, the project team, and the key project stakeholders have completed a round of qualitative risk analysis.
He needs to update the risk register with his findings so that he can communicate the risk results to the project stakeholders - including management. Mark will need to update all of the following information except for which one?
A.
Watchlist of low-priority risks
B.
Prioritized list of quantified risks
C.
Risks grouped by categories
D.
Trends in qualitative risk analysis