Question 292 - CAP discussion
Jenny is the project manager for the NBT projects. She is working with the project team and several subject matter experts to perform the quantitative risk analysis process. During this process she and the project team uncover several risks events that were not previously identified. What should Jenny do with these risk events?
A.
The events should be determined if they need to be accepted or responded to.
B.
The events should be entered into qualitative risk analysis.
C.
The events should continue on with quantitative risk analysis.
D.
The events should be entered into the risk register.
Your answer: