You work as a project manager for BlueWell Inc. You with your team are using a method or a (technical) process that conceives the risks even if all theoretically possible safety measures would be applied. One of your team member wants to know that what is a residual risk. What will you reply to your team member?

A.
It is a risk that remains because no risk response is taken.
Answers
A.
It is a risk that remains because no risk response is taken.
B.
It is a risk that remains after planned risk responses are taken.
Answers
B.
It is a risk that remains after planned risk responses are taken.
C.
It is a risk that can not be addressed by a risk response.
Answers
C.
It is a risk that can not be addressed by a risk response.
D.
It is a risk that will remain no matter what type of risk response is offered.
Answers
D.
It is a risk that will remain no matter what type of risk response is offered.
Suggested answer: B