List of questions
Related questions
Question 308 - CAP discussion
Diane is the project manager of the HGF Project. A risk that has been identified and analyzed in the project planning processes is now coming into fruition. What individual should respond to the risk with the preplanned risk response?
A.
Diane
B.
Risk owner
C.
Subject matter expert
D.
Project sponsor
Your answer:
0 comments
Sorted by
Leave a comment first