Question 314 - CAP discussion
You and your project team have identified the project risks and now are analyzing the probability and impact of the risks. What type of analysis of the risks provides a quick and high-level review of each identified risk event?
A.
Qualitative risk analysis
B.
Seven risk responses
C.
Quantitative risk analysis
D.
A risk probability-impact matrix
Your answer: