You are the project manager of the NNN project for your company. You and the project team are working together to plan the risk responses for the project. You feel that the team has successfully completed the risk response planning and now you must initiate what risk process it is. Which of the following risk processes is repeated after the plan risk responses to determine if the overall project risk has been satisfactorily decreased?

A.
Risk identification
Answers
A.
Risk identification
B.
Qualitative risk analysis
Answers
B.
Qualitative risk analysis
C.
Risk response implementation
Answers
C.
Risk response implementation
D.
Quantitative risk analysis
Answers
D.
Quantitative risk analysis
Suggested answer: D