You work as a project manager for BlueWell Inc. You are working on a project and the management wants a rapid and cost-effective means for establishing priorities for planning risk responses in your project. Which risk management process can satisfy management's objective for your project?
A.
Qualitative risk analysis
B.
Quantitative analysis
C.
Historical information
D.
Rolling wave planning
Your answer: