Which of the following processes is described in the statement below?

"It is the process of implementing risk response plans, tracking identified risks, monitoring residual risk, identifying new risks, and evaluating risk process effectiveness throughout the project."

A.
Perform Quantitative Risk Analysis
Answers
A.
Perform Quantitative Risk Analysis
B.
Monitor and Control Risks
Answers
B.
Monitor and Control Risks
C.
Perform Qualitative Risk Analysis
Answers
C.
Perform Qualitative Risk Analysis
D.
Identify Risks
Answers
D.
Identify Risks
Suggested answer: B