ExamGecko
Home Home / ISC / CAP
Question list
Search
Search

List of questions

Search

Related questions











Question 383 - CAP discussion

Report
Export

You work as a project manager for BlueWell Inc. There has been a delay in your project work that is adversely affecting the project schedule. You decided, with your stakeholders' approval, to fast track the project work to get the project done faster. When you fast track the project which of the following are likely to increase?

A.
Risks
Answers
A.
Risks
B.
Human resource needs
Answers
B.
Human resource needs
C.
Quality control concerns
Answers
C.
Quality control concerns
D.
Costs
Answers
D.
Costs
Suggested answer: A
asked 18/09/2024
Muhammad Imran
41 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first