Question 388 - CAP discussion
During which of the following processes, probability and impact matrix is prepared?
A.
Plan Risk Responses
B.
Perform Quantitative Risk Analysis
C.
Perform Qualitative Risk Analysis
D.
Monitoring and Control Risks
Your answer: