Which value refers to the amount of data an organization would need to recover in the event of a BCDR situation in order to reach an acceptable level of operations?

A.
SRE
Answers
A.
SRE
B.
RTO
Answers
B.
RTO
C.
RPO
Answers
C.
RPO
D.
RSL
Answers
D.
RSL
Suggested answer: C

Explanation:

The recovery point objective (RPO) is defined as the amount of data a company would need to maintain and recover in order to function at a level acceptable to management. This may or may not be a restoration to full operating capacity, depending on what management deems as crucial and essential.