Just like the risk management process, the BCDR planning process has a defined sequence of steps and processes to follow to ensure the production of a comprehensive and successful plan.

Which of the following is the correct sequence of steps for a BCDR plan?

A.
Define scope, gather requirements, assess risk, implement
Answers
A.
Define scope, gather requirements, assess risk, implement
B.
Define scope, gather requirements, implement, assess risk
Answers
B.
Define scope, gather requirements, implement, assess risk
C.
Gather requirements, define scope, implement, assess risk
Answers
C.
Gather requirements, define scope, implement, assess risk
D.
Gather requirements, define scope, assess risk, implement
Answers
D.
Gather requirements, define scope, assess risk, implement
Suggested answer: A

Explanation:

The correct sequence for a BCDR plan is to define the scope, gather requirements based on the scope, assess overall risk, and implement the plan. The other sequences provided are not in the correct order.