Question 890 - CISSP discussion
An audit of an application reveals that the current configuration does not match the configuration of the originally implemented application. Which of the following is the FIRST action to be taken?
A.
Recommend an update to the change control process.
B.
Verify the approval of the configuration change.
C.
Roll back the application to the original configuration.
D.
Document the changes to the configuration.