What is the MAIN objective of risk analysis in Disaster Recovery (DR) planning?

A.
Establish Maximum Tolerable Downtime (MTD) Information Systems (IS).
Answers
A.
Establish Maximum Tolerable Downtime (MTD) Information Systems (IS).
B.
Define the variable cost for extended downtime scenarios.
Answers
B.
Define the variable cost for extended downtime scenarios.
C.
Identify potential threats to business availability.
Answers
C.
Identify potential threats to business availability.
D.
Establish personnel requirements for various downtime scenarios.
Answers
D.
Establish personnel requirements for various downtime scenarios.
Suggested answer: C