List of questions
Related questions
Question 1147 - CISSP discussion
An organization's retail website provides its only source of revenue, so the disaster recovery plan (DRP) must document an estimated time for each step in the plan.
Which of the following steps in the DRP will list the GREATEST duration of time for the service to be fully operational?
A.
Update the Network Address Translation (NAT) table.
B.
Update Domain Name System (DNS) server addresses with domain registrar.
C.
Update the Border Gateway Protocol (BGP) autonomous system number.
D.
Update the web server network adapter configuration.
Your answer:
0 comments
Sorted by
Leave a comment first