When designing a business continuity plan (BCP), what is the formula to determine the Maximum Tolerable Downtime (MTD)?

A.
Annual Loss Expectancy (ALE) + Work Recovery Time (WRT)
Answers
A.
Annual Loss Expectancy (ALE) + Work Recovery Time (WRT)
B.
Business impact analysis (BIA) + Recovery Point Objective (RPO)
Answers
B.
Business impact analysis (BIA) + Recovery Point Objective (RPO)
C.
Recovery Time Objective (RTO) + Work Recovery Time (WRT)
Answers
C.
Recovery Time Objective (RTO) + Work Recovery Time (WRT)
D.
Estimated Maximum Loss (EML) + Recovery Time Objective (RTO)
Answers
D.
Estimated Maximum Loss (EML) + Recovery Time Objective (RTO)
Suggested answer: C