At which phase of the software assurance life cycle should risks associated with software acquisition strategies be identified?

A.
Follow-on phase
Answers
A.
Follow-on phase
B.
Planning phase
Answers
B.
Planning phase
C.
Monitoring and acceptance phase
Answers
C.
Monitoring and acceptance phase
D.
Contracting phase
Answers
D.
Contracting phase
Suggested answer: C