Which of the following plans is a comprehensive statement of consistent actions to be taken before, during, and after a disruptive event that causes a significant loss of information systems resources?

A.
Disaster recovery plan
Answers
A.
Disaster recovery plan
B.
Contingency plan
Answers
B.
Contingency plan
C.
Business Continuity plan
Answers
C.
Business Continuity plan
D.
Continuity of Operations plan
Answers
D.
Continuity of Operations plan
Suggested answer: A