An administrator accidentally closed the commit window/screen before the commit was finished.

Which two options could the administrator use to verify the progress or success of that commit task?

(Choose two.)

A.
System Logs
Answers
A.
System Logs
B.
Task Manager
Answers
B.
Task Manager
C.
Traffic Logs
Answers
C.
Traffic Logs
D.
Configuration Logs
Answers
D.
Configuration Logs
Suggested answer: A, B

Explanation:

A. System Logs: The system logs contain information about various events that occur on the firewall, including the commit process. The administrator can review the system logs to verify whether the commit completed successfully or whether there were any errors or warnings during the commit process.

B. Task Manager: The task manager displays a list of all active tasks on the firewall, including the commit task. The administrator can use the task manager to check the status of the commit task, including whether it is in progress, completed successfully, or failed.