ExamGecko
Question list
Search
Search

List of questions

Search

Related questions











Question 63 - Certified MuleSoft Integration Architect I discussion

Report
Export

An organization's governance process requires project teams to get formal approval from all key stakeholders for all new Integration design specifications. An integration Mule application Is being designed that interacts with various backend systems. The Mule application will be created using Anypoint Design Center or Anypoint Studio and will then be deployed to a customer-hosted runtime.

What key elements should be included in the integration design specification when requesting approval for this Mule application?

A.
SLAs and non-functional requirements to access the backend systems
Answers
A.
SLAs and non-functional requirements to access the backend systems
B.
Snapshots of the Mule application's flows, including their error handling
Answers
B.
Snapshots of the Mule application's flows, including their error handling
C.
A list of current and future consumers of the Mule application and their contact details
Answers
C.
A list of current and future consumers of the Mule application and their contact details
D.
The credentials to access the backend systems and contact details for the administrator of each system
Answers
D.
The credentials to access the backend systems and contact details for the administrator of each system
Suggested answer: A

Explanation:

SLAs and non-functional requirements to access the backend systems. Only this option actually speaks to design parameters and reqs.*Below two are technical implementations and not the part of design: - Snapshots of the Mule application's flows, including their error handling - The credentials to access the backend systems and contact details for the administrator of each system*List of consumers is not relevant to the design

asked 23/09/2024
Sivakumar Balasundram
41 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first