Universal Containers (UC) has a time-sensitive need for a custom component to be built in 4 weeks; UC developers require additional enablement to complete the work and are backlogged by several months.
Which option should an app builder suggest to meet this requirement?
A.
Use an AppExchange solution.
B.
Build a screen flow page.
C.
Build a Lightning record page.
D.
Use a Boit solution