What are the terms for level of risk before and after any actions are taken? (Choose two.)

A.
Operational risk
Answers
A.
Operational risk
B.
Digital risk
Answers
B.
Digital risk
C.
Inherent risk
Answers
C.
Inherent risk
D.
Calculated risk
Answers
D.
Calculated risk
E.
Residual risk
Answers
E.
Residual risk
F.
Solutioned risk
Answers
F.
Solutioned risk
Suggested answer: A, E