Upon completion and validation of an improvement to a process a Belt and the Project Team create a Control Plan that contains which of these?

A.
Standard operating work description of the process change
Answers
A.
Standard operating work description of the process change
B.
Description of the monitoring system in place to assure continued compliance
Answers
B.
Description of the monitoring system in place to assure continued compliance
C.
Summary of the targeted critical metrics for process performance measurement
Answers
C.
Summary of the targeted critical metrics for process performance measurement
D.
All of the above
Answers
D.
All of the above
Suggested answer: D