Which of the following has to be done in the project requirements analysis?

A.
The business or organizational requirements and opportunities are first identified and then are converted into project requirements.
Answers
A.
The business or organizational requirements and opportunities are first identified and then are converted into project requirements.
B.
The requirements analysis considers the whole range of the project and examines the requirements and ideas of all the project stakeholders.
Answers
B.
The requirements analysis considers the whole range of the project and examines the requirements and ideas of all the project stakeholders.
C.
Once the requirement analysis is completed, it should be evaluated and accepted by the customer or the project sponsor.
Answers
C.
Once the requirement analysis is completed, it should be evaluated and accepted by the customer or the project sponsor.
D.
All of the above.
Answers
D.
All of the above.
Suggested answer: D