Which of the following is not a time estimates for PERT?

A.
Pessimistic time
Answers
A.
Pessimistic time
B.
Most likely time
Answers
B.
Most likely time
C.
Optimistic time
Answers
C.
Optimistic time
D.
Waiting time
Answers
D.
Waiting time
Suggested answer: D