Which statement(s) describe an undesirable situation when implementing SPC?

A.
The lower Control Limit for the R chart is equal to zero
Answers
A.
The lower Control Limit for the R chart is equal to zero
B.
Attempt to use SPC for tracking transaction times at a warehouse
Answers
B.
Attempt to use SPC for tracking transaction times at a warehouse
C.
A process is in Statistical Control before implementation of SPC
Answers
C.
A process is in Statistical Control before implementation of SPC
D.
The Control Limits are wider than the customer specification limits
Answers
D.
The Control Limits are wider than the customer specification limits
Suggested answer: D