The Project viewpoint is primarily used to model the management of architecture change.
Which one of the following cannot be shown in a Project view?
A.
Resourcing of projects
B.
The main differences between the baseline and the target architecture
C.
The motivation for projects
D.
The results produced by different projects
Your answer: