ExamGecko
Question list
Search
Search

Question 74 - OG0-091 discussion

Report
Export

Which phase of the ADM is an on-going activity that is visited throughout a TOGAF architecture project?

A.
Architecture Change Management
Answers
A.
Architecture Change Management
B.
Implementation governance
Answers
B.
Implementation governance
C.
Migration planning
Answers
C.
Migration planning
D.
Preliminary Phase
Answers
D.
Preliminary Phase
E.
Requirements Management
Answers
E.
Requirements Management
Suggested answer: E
asked 23/09/2024
NSANG Cyril
34 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first