What is an objective of ADM Phase G, Implementation Governance?
A.
To ensure that implementation projects conform with the Target Architecture
B.
To ensure that the enterprise's Architecture Capability meets current requirements
C.
To assess the performance of the architecture and make recommendations for change
D.
To establish the value realization process
E.
To prioritise the projects through risk validation