In which Phase of the TOGAF ADM is the focus the creation of an Implementation and Migration Plan in co-operation with the portfolio and project managers?

A.
Phase F
Answers
A.
Phase F
B.
Phase D
Answers
B.
Phase D
C.
Phase G
Answers
C.
Phase G
D.
Phase E
Answers
D.
Phase E
E.
Phase A
Answers
E.
Phase A
Suggested answer: A

Explanation:

Reference: http://pubs.opengroup.org/architecture/togaf91-doc/arch/chap14.html