Which phase of the ADM is an on-going activity that is visited throughout a TOGAF architecture project?

A.
Architecture Change Management
Answers
A.
Architecture Change Management
B.
Implementation governance
Answers
B.
Implementation governance
C.
Migration planning
Answers
C.
Migration planning
D.
Preliminary Phase
Answers
D.
Preliminary Phase
E.
Requirements Management
Answers
E.
Requirements Management
Suggested answer: E