In which ADM phase does the value and change management process determine the circumstances under which the Architecture Development Cycle will be initiated to develop a new architecture?

A.
Phase F
Answers
A.
Phase F
B.
Phase E
Answers
B.
Phase E
C.
Phase G
Answers
C.
Phase G
D.
Phase H
Answers
D.
Phase H
E.
Preliminary Phase
Answers
E.
Preliminary Phase
Suggested answer: D