Please read this scenario prior to answering the question You are the Lead Enterprise Architect at a major agribusiness company. The company's main annual harvest is lentils, a highly valued food grown worldwide. The lentil parasite, broomrape, has been an increasing concern for many years and is now becoming resistant to chemical controls. In addition, changes in climate favor the propagation and growth of the parasite. As a result, the parasite cannot realistically be exterminated, and it has become pandemic, with lentil yields falling globally. The CEO appreciates the seriousness of the situation and has set out a change in direction that is effectively a new business for the company. There are opportunities for new products, and new markets. The company will use the fields for another harvest and will cease to process third-party lentils. Thus, the target market will change, and the end-products will be different and more varied. This is a major decision and the CEO has stated a desire to repurpose rather than replace so as to manage the risks and limit the costs. The company has a mature Enterprise Architecture practice based in its headquarters and uses the TOGAF standard as the method and guiding framework. The practice has an established Architecture Capability, and uses iteration for architecture development. The CIO is the sponsor of the activity. The CIO has assigned the Enterprise Architecture team to this activity. At this stage there is no shared vision, or requirements. Refer to the scenario You have been asked to propose the best approach for architecture development to realize the CEO's change in direction for the company. Based on the TOGAF standard which of the following is the best answer?






Question 64 - OGEA-10B discussion

Report
Export

Exhibit

Consider the illustration showing an architecture development cycle Which description matches the phase of the ADM labeled as item 2?

A.
Conducts implementation planning for the architecture defined in previous phases
Answers
A.
Conducts implementation planning for the architecture defined in previous phases
B.
Establishes procedures for managing change to the new architecture
Answers
B.
Establishes procedures for managing change to the new architecture
C.
Operates the process of managing architecture requirements
Answers
C.
Operates the process of managing architecture requirements
D.
Provides architectural oversight for the implementation
Answers
D.
Provides architectural oversight for the implementation
Suggested answer: D

Explanation:

Based on the illustration, the phase of the ADM labeled as item 2 is the Implementation Governance phase. This phase provides architectural oversight for the implementation. It ensures that the implementation project conforms to the architecture. It also provides a framework for monitoring and managing the implementation.

The Implementation Governance phase involves the following activities:

Finalizing the Architecture Roadmap and the supporting Implementation and Migration Plan

Assigning an Architecture Board to oversee the implementation

Establishing Architecture Contracts with the implementation partners

Reviewing and approving the implementation project plans and deliverables

Performing Architecture Compliance reviews to ensure alignment with the architecture

Performing Architecture Audit reviews to ensure quality and performance of the architecture

Resolving any architecture issues or change requests that arise during the implementation

Maintaining the architecture lifecycle and ensuring its continuity

The Implementation Governance phase is essential for ensuring that the architecture is realized as intended and that it delivers the expected business value and outcomes.