Question 50 - 220-010 discussion
You are using expandable resource pools in your VMware cluster to ensure each environment is allocated the appropriate resources. There is a resource pool for your development environment that has a reservation of 5 GHz CPU and 12 GB of memory. There is a child resource pool of the development resource pool named Sandbox that has a reservation of 1 GHz CPU and 4 GB of memory. You create four new virtual machines with 4 GB of memory in the Sandbox environment.
In this scenario, which statement is true?
A.
Only one of the new virtual machines will power on.
B.
All new virtual machines will power on.
C.
Only three of the new virtual machines will power on.
D.
No new virtual machines will power on.