A company has outgrown their current data center and plans to use the second data center as the new primary and needs to migrate their workloads. They are running VMware in both data centers.

Which steps would allow this migration to occur without any data loss?

A.
1. Replication job 2. Failover plan 3. Permanent failover
Answers
A.
1. Replication job 2. Failover plan 3. Permanent failover
B.
1. Backup job 2. Instant VM Recovery 3. Finalize the Instant VM Recovery
Answers
B.
1. Backup job 2. Instant VM Recovery 3. Finalize the Instant VM Recovery
C.
1. Replication job 2. Failback 3. Commit failback
Answers
C.
1. Replication job 2. Failback 3. Commit failback
D.
1. Replication job 2. Planned failover 3. Permanent failover
Answers
D.
1. Replication job 2. Planned failover 3. Permanent failover
Suggested answer: D

Explanation:

https://helpcenter.veeam.com/docs/backup/vsphere/planned_failover.html?ver=100