A consultant needs to verify the make and model of the systems that will be imaged with Foundation. The consultant does not have the Bill of Materials (BOM) available to review.

When should the consultant verify the make and model to prepare for the cluster deployment?

A.
During the Foundation Process
Answers
A.
During the Foundation Process
B.
While conducting the Tech Review Call
Answers
B.
While conducting the Tech Review Call
C.
Upon arriving on-site
Answers
C.
Upon arriving on-site
D.
When reviewing the Statement of Work (SOW)
Answers
D.
When reviewing the Statement of Work (SOW)
Suggested answer: B

Explanation:

The make and model of the systems should be verified during the Tech Review Call. This step is essential to ensure that all necessary information is collected and verified before any physical interaction with the hardware. Verifying these details during the call helps in preparing adequately for the cluster deployment, allowing the consultant to anticipate and mitigate any compatibility or configuration issues before arriving onsite.

Reference: Nutanix Foundation Guide, Pre-installation Checklist Documents.