A consultant is planning an installation and needs to collect configuration items to be used during the install. The data needed from the customer are IP addresses, Gateway, DNS servers, and NTP Servers.

Which Cluster Deployment document must be completed with the customer?

A.
Project Plan
Answers
A.
Project Plan
B.
Operations Guide
Answers
B.
Operations Guide
C.
Questionnaire
Answers
C.
Questionnaire
D.
Technical Checklist
Answers
D.
Technical Checklist
Suggested answer: D

Explanation:

The document that needs to be completed with the customer to collect configuration items such as IP addresses, Gateway, DNS servers, and NTP Servers is the Technical Checklist. This checklist is designed to ensure all necessary technical information is gathered prior to the installation, enabling a smooth and efficient setup process.

Reference: Nutanix Cluster Deployment Guide, Pre-installation Planning Documentation.