An existing Nutanix customer has several clusters in production and is adding a new cluster. The customer wants to create an AHV cluster that has already been racked and powered on remotely, with the factory image, using Prism Central.
Which step should the consultant take next?
A.
Build the cluster with the Foundation Applet
B.
Build the cluster with the Foundation VM.
C.
Bare metal image the nodes with the Foundation VM.
D.
Build the cluster with Foundation Central.