After finishing customer education during a new cluster deployment, the consultant wants to make sure all in-scope tasks have been completed.

Which document can the consultant use to verify all tasks have been closed out?

A.
As-Built Guide
Answers
A.
As-Built Guide
B.
Deployment Questionnaire
Answers
B.
Deployment Questionnaire
C.
Deployment Guide
Answers
C.
Deployment Guide
D.
Deployment Checklist
Answers
D.
Deployment Checklist
Suggested answer: D

Explanation:

To verify that all in-scope tasks for a new cluster deployment have been completed, the consultant should refer to the:

Deployment Checklist: This document typically lists all tasks required for a successful deployment, making it a suitable tool for ensuring that nothing has been overlooked.

Nutanix Bible (https://www.nutanixbible.com), where the importance of deployment documentation is discussed.

Nutanix Deployment Guide, which includes detailed checklists for ensuring thorough project completion.