A consultant is working to setup the network before starting the Foundation process.

How should the consultant complete this task?

A.
Using the shared IPMI port, ensure that the connected switch can auto-negotiate to 1 Gbps.
Answers
A.
Using the shared IPMI port, ensure that the connected switch can auto-negotiate to 1 Gbps.
B.
Disable IPv6 on the network to which the nodes are connected to ensure that IPv6 unicast is blocked.
Answers
B.
Disable IPv6 on the network to which the nodes are connected to ensure that IPv6 unicast is blocked.
C.
Ensure the IPMI of the nodes are reachable using pre-configured IPMI IPv6 addresses.
Answers
C.
Ensure the IPMI of the nodes are reachable using pre-configured IPMI IPv6 addresses.
D.
On Nutanix NX Series, connect the IPMI port and any one of the data ports to the switch.
Answers
D.
On Nutanix NX Series, connect the IPMI port and any one of the data ports to the switch.
Suggested answer: D

Explanation:

Before starting the Foundation process, the consultant should prepare the network by:

On Nutanix NX Series, connect the IPMI port and any one of the data ports to the switch: This ensures that the IPMI (for management and remote access) and at least one data port (for cluster communication and data traffic) are connected and operational, facilitating a smooth foundation process.

Nutanix Bible (https://www.nutanixbible.com), especially sections on initial hardware setup and network preparations.

Nutanix Hardware Setup Guide from Nutanix University (https://university.nutanix.com), detailing the specific steps for networking configurations during initial setup.