Question 231 - NCS-Core discussion
A consultant is working to setup the network before starting the Foundation process.
How should the consultant complete this task?
A.
Using the shared IPMI port, ensure that the connected switch can auto-negotiate to 1 Gbps.
B.
Disable IPv6 on the network to which the nodes are connected to ensure that IPv6 unicast is blocked.
C.
Ensure the IPMI of the nodes are reachable using pre-configured IPMI IPv6 addresses.
D.
On Nutanix NX Series, connect the IPMI port and any one of the data ports to the switch.