Question 264 - NCS-Core discussion

Report
Export

The installation process stops before imaging any of the nodes and an error message is displayed notifying the IPMI IP address is unreachable.

What should consultant do to fix the issue?

A.
Ensure the Foundation VM is not in the same broadcast domain as the Controller VMs.
Answers
A.
Ensure the Foundation VM is not in the same broadcast domain as the Controller VMs.
B.
Re-try Foundation using a non-flat switch.
Answers
B.
Re-try Foundation using a non-flat switch.
C.
Check the service. log and the individual node log files for more detailed information.
Answers
C.
Check the service. log and the individual node log files for more detailed information.
D.
if the nodes are in the same subnet go to the Cluster page and configure multi-homing.
Answers
D.
if the nodes are in the same subnet go to the Cluster page and configure multi-homing.
Suggested answer: C

Explanation:

When facing an error during the installation process that the IPMI IP address is unreachable:

C . Check the service.log and the individual node log files for more detailed information: Reviewing these log files will provide insights into what might be causing the IPMI connectivity issue, offering specific error messages or network configuration problems that need resolution.

Nutanix Bible (https://www.nutanixbible.com), where troubleshooting and log analysis are discussed.

Nutanix University: NCS-Core 6.8 Training (https://university.nutanix.com), focusing on Foundation troubleshooting and the use of log files to diagnose installation issues.

asked 23/09/2024